Project Name | Four laning of Phagwara-Rupnagar Section of NH-344A from Km 0.00 to Km 80.820 in the State of Punjab on Hybrid Annuity Mode. |
---|---|
NH No. (New/ Old) | 344A |
Scheme/ Phase | NHDP Phase – IV |
Mode of the Execution | Hybrid Annuity Mode (HAM) |
No. of Lanes/ Configuration | Four Lane With Paved Shoulder |
Length of the Project | 80.820 Km. |
Total Project Cost | INR 1367 Cr. |
No. of Bypasses (Name of Town, Length) | 1 Nos (Nawanshahr Bye pass- 10 kms) and 1.245. KM Re-alignment (Garhi) |
No. of Major Bridges (Number and Location) | Major Bridges -01 Nos (km. 59+381) Minor Bridges- 22 Nos (km. 35+812, km. 38+326, km. 48+323, km. 57+981, km. 59+237, km. 62+704, km. 63+615, km. 64+791, km. 66+020, km. 68+519, km. 69+815, km. 71+174, km. 71+727, km. 72+134, km. 72+900, km. 74+173, km. 74+361, km. 75+009, km. 76+815, km. 77+613, km. 78+636, km. 80+045 |
No. of Toll Plazas (Number and Location) | 02 Nos. (Toll Plaza at Ch. 15+300 & Km. 70+240) |
No. Of Culverts | 91 Nos |
No. of Fly Overs/Under Passes (Number and Location) | Fly Over- 04 No (Km 4+225, km. 9+335, km. 39+915, km. 59+818). Under Passes (VUP/PUP)-02 Nos. (Km.-6+930 & Km.32+487), |
No. of Elevated Structure / ROB (Number and Location) | Elevated Structure – 01 Nos (Km. 25+319 To 28+333) ROB -01 Nos (Km. 39+133.7) |
DPR Consultant Name | M/S Indian Technocrat Ltd. |
Concessionaire Name (SPV & Parent Company) | M/S GR Phagwara Expressway Limited (GRPEL) & M/S G R Infraprojects Limited (GRIL) |
Date of Letter of Award (LOA) | 22nd August 2016 |
Appointed Date | 06th October 2017 |
Concession Period | 15 Years |
Construction Period (in Days) | 910 Days |
O&M Period (in Days) | 15 Years |
Scheduled Date of Completion | 03rd April 2020 |
Independent Engineer | TPF GETINSA EUROESTUDIOS, S.L. In association with Segmental Consulting & Infrastructure Advisory Pvt. Ltd. |
IE Agreement Date | 19th June, 2017 |
IE Mobilization Date | 21st June, 2017 |